RFI-to-Field Impact Analytics for Mega-Terminal Structural Packages: A Traceability Model Linking RFIs, Revisions, and Schedule Impacts

Authors

  • Rukmini Reddy Sama Construction Management and Civil Engineering · IEEE Author

DOI:

https://doi.org/10.56830/IJSIE202618

Keywords:

Data-driven model, requests for information (RFIs), record linkage, predictive analytics, construction rework, schedule delays, airport megaprojects, synthetic benchmark

Abstract

Requests for Information (RFIs) can delay and complicate large construction projects, yet their downstream effects on design revisions, field rework, and schedule are rarely traced. This paper proposes an RFI-to-field traceability framework for airport Project Management/Construction Management (PMCM) teams. The framework links each RFI to the resulting drawing revisions, field change orders (FCOs), Non-Conformance Reports (NCRs), rework, and critical-path delay across four project systems (Procore, Oracle Unifier, Primavera P6, and Bluebeam), and adds a leakage-aware classifier that assigns each RFI to a low, medium, or high impact class using only information available at submission. Because the logs of the motivating airport case are confidential, the framework is evaluated on a synthetic benchmark of 2,400 RFIs over 48 months with known ground-truth links; the results therefore validate the pipeline and are not empirical findings about real projects. The tiered linkage recovered 89%–99% of true links at each stage, with precision of 57%–96% (lowest for NCR and schedule links), and linkage-derived impact labels agreed with ground truth (Cohen's κ = 0.88). With a time-ordered split, the best early-warning model (random forest) reached a macro-F1 of 0.39 (95% CI 0.36–0.43) and ROC-AUC of 0.62 against a macro-F1 of 0.26 for a majority-class baseline, i.e., weak discrimination under the assumed noise. No cost or schedule saving is claimed; replication on anonymized real logs with a manual link audit is required.

References

Abdulfattah, B. S., & et al. (2023). "Predicting implications of design changes in BIM-based construction projects through machine learning," . Autom. Constr, doi: 10.1016/j.autcon.2023.105057.

Afzal, M., Wong, J., & A. A. Fard Fini. (2024). "Towards digital approach for managing request for information (RFI) in construction projects: a literature review,". Constr. Innov, doi: 10.1108/ci-05-2023-0113. https://www.emerald.com/ci/article/25/5/1345/1252783.

Aibinu, A. A., Carter, S., Francis, V., & P. Vaz-Serra. (2019). "Request for information frequency and their turnaround time in construction projects,". Built Environ. Proj. Asset Manag, doi:

1108/bepam-10-2018-0130. https://www.emerald.com/bepam/article/10/1/1/63591.

Akinosho, T., & et al. (2020). "Deep learning in the construction industry: a review of present status and future innovations,". J. Build. Eng, doi: 10.1016/j.jobe.2020.101827.

Alshboul, O., Shehadeh, A., Mamlook, R. E., Almasabha, G., Almuflih, A. S., & S. Y. Alghamdi. (2022). "Prediction liquidated damages via ensemble machine learning model: Towards sustainable highway construction projects,". Sustainability, vol. 14, no. 15, Art. no. 9303, 2022, doi: 10.3390/su14159303.

Al-Sinan, M. A., Bubshait, A. A., & Z. Aljaroudi. (2024). "Generation of construction scheduling through machine learning and BIM: a blueprint," . Buildings, doi: 10.3390/buildings14040934.

Baduge, S. K., & et al. (2022). "Artificial intelligence and smart vision for building and construction 4.0: machine and deep learning methods and applications," . Autom. Constr, doi: 10.1016/j.autcon.2022.104440.

Bucher, D. F., Hunhevicz, J. J., Soman, R. K., Pauwels, P., & D. M. Hall. (2024). “From BIM to Web3: A critical interpretive synthesis of present and emerging data management approaches in construction informatics,”. Advanced Engineering Informatics, vol. 62, Art. no. https://www.sciencedirect.com/science/article/pii/S1474034624005329.

G. K. Koulinas, A. X. (2020). "Schedule delay risk analysis in construction projects with a simulation-based expert system," . Buildings, doi: 10.3390/buildings10080134.

Hegazy, T., Said, M., & M. Kassab. (2011). "Incorporating rework into construction schedule analysis,". Autom. Constr, doi: 10.1016/j.autcon.2011.04.006. https://www.sciencedirect.com/science/article/pii/S0926580511000550.

Hwang, B.-G., & L. P. Leong. (2023). "Comparison of schedule delay and causal factors between traditional and green construction projects,". Technol. Econ. Dev. Econ, doi: 10.3846/20294913.2013.798596.

Joy, L. P., Zarei, F., & M. Nik-Bakht. (2026). “Semantic mapping of Request for Information (RFI) to BIM elements with large language models,” in. Proc. 2026 European Conf. Computing in Construction (EC3), Corfu, Greece, Jul. , 12–15, doi: 10.35490/EC3.2026.337.

Kim, J. J., Petrov, A., Lim, J., & S. Kim. (2021). "Comparing cost performance of project delivery methods using quantifiable RFIs: cases in California heavy civil construction projects,". Int. J. Civ. Eng, doi: 10.1007/s40999-021-00658-0.

Kocakaya, M. N., Namlı, E., & Ü. Işıkdağ. (2019). "Building information management (BIM), a new approach to project management," . J. Sustain. Constr. Mater. Technol, doi: 10.29187/jscmt.2019.36.

Kor, M., Yitmen, İ., & S. Alizadehsalehi. (2022). "An investigation for integration of deep learning and digital twins towards Construction 4.0,". Smart Sustain. Built Environ, doi: 10.1108/sasbe-08-2021-0148.

Ma, G., Jiang, S., Zhu, T., & J. Jia. (2019). "A novel method of developing construction projects schedule under rework scenarios,". Sustainability, doi: 10.3390/su11205710.

Olawumi, T. O., & D. W. M. Chan. (2019). "Building information modelling and project information management framework for construction projects,". J. Civ. Eng. Manag, doi: 10.3846/jcem.2019.7841. https://journals.vilniustech.lt/index.php/JCEM/article/download/7841/6987.

Othman, A. A., & M. S. Ali. (2024). “Managing design changes through integrating concurrent engineering into the architectural design process,”. Int. J. Eng.Res. Afr, vol. pp.

117–140, https://buescholar.bue.edu.eg/cgi/viewcontent.cgi?article=1255&context=arch_eng.

Panahi, R., Kivlin, J.-P., & J. Louis. (2023). “Request for Information (RFI) recommender system for pre-construction design review application using natural language processing, Chat-GPT, and computer vision,”. in Computing in Civil Engineering, Data, Sensing, and Analytics, Corvallis, OR, USA, 2024, pp. 159–166.

Papajohn, D., & M. El Asmar. (2021). "Impact of alternative delivery on the response time of requests for information for highway projects,". J. Manag. Eng, doi: 10.1061/(asce)me.1943-5479.0000866. https://ascelibrary.org/doi/abs/10.1061/(ASCE)ME.1943-5479.0000866.

Pinto, H. A., & t al. (2026). "A review on BIM’s contribution to an efficient RFI management in complex geotechnical and construction projects,". Discov. Civ. Eng, doi: 10.1007/s44290-026-00542-7.

Sandoval, I. S., Bernardo, J. P., Dionisio, S. R., & A. H. Aquino. (2023). “Application of Information and Communication Technologies (ICT) to optimize the request for information (RFI) process in construction projects,”. in Proc. 2023 9th Int. Conf. Innovation and Trends in Engineering (CONIITI), Bogotá, Colombia, https://ieeexplore.ieee.org/abstract/document/10324094/.

Soliman, E., Alrasheed, K. A., Alghanim, S., & E. Morsi. (2019). “Integrating risk management and earned value framework to detect early warning signs—Case study,”. Journal of Engineering Research, vol. 13, no. 3, pp. 2109–2116, 2025. https://www.sciencedirect.com/science/article/pii/S2307187724001421.

Yap, J. B., Abdul-Rahman, H., & W. Chen. (2017). "Collaborative model: managing design changes with reusable project experiences through project learning and effective communication,". Int. J. Proj. Manag, doi: 10.1016/j.ijproman.2017.04.010.

Yilmaz, N., Ergen, E., & A. M. Citipitioglu. (2025). “Enhancing RFI management in construction through machine learning-driven predictive models,”. Smart and Sustainable Built Environment, pp. 1–21, 2025. https://www.emerald.com/sasbe/article/doi/10.1108/SASBE-05-2025.

Downloads

Published

2026-11-11

Issue

Section

Articles