Integrated Cost-Schedule-Procurement Risk Index: A Framework and Validation Protocol for Hyper-Scale Data-Center Construction

Authors

  • Ravi Charan Kattula Construction Management and Civil Engineer, Texas, United States Author

DOI:

https://doi.org/10.56830/IJSIE202619

Keywords:

Hyperscale Data Centers, Construction Risk Management, Early-Warning Systems, Earned Value Management, Integrated Risk Index

Abstract

Hyperscale data-center projects combine high capital cost, compressed schedules, specialized long-lead equipment, and global supply chains. Conventional project controls review cost, schedule, procurement, and operational measures separately, so deterioration that starts upstream, for example in procurement, may appear in the Cost Performance Index (CPI) and Schedule Performance Index (SPI) only after it has become costly to recover. This paper proposes the Integrated Cost-Schedule-Procurement Risk Index (ICSP-RI), a composite early-warning index for hyperscale data-center construction, together with a protocol for developing and validating it. The framework starts from 42 candidate indicators in four categories (cost, schedule, procurement, and operational), which are screened, normalized to a common 0–1 risk scale, weighted, and aggregated into a project-level score. The paper specifies the normalization and aggregation formulas, the procedure for estimating weights, provisional risk classes, and a validation design that compares the index with CPI and SPI alone and with a baseline model that combines CPI, SPI, and the procurement variables. Because real project records could not be used, the protocol is demonstrated on synthetic data from a simulation of 40 projects over 24 monthly periods in three scenarios. The demonstration shows that the pipeline runs end to end and behaves sensibly: the index is more accurate than earned-value indicators alone when procurement or operational signals carry information, and shows no gain when they do not. However, the composite performs about as well as using all retained indicators without aggregation, and in the scenario where procurement and execution stress both drive outcomes, it did not meet the pre-specified criterion of improving on a baseline that combines earned-value and procurement indicators. No results from real projects are reported, and the simulation results follow from its stated assumptions.

References

Abdulaziz, H., & Ahmed, H. M. (2026). A customized business intelligence dashboard utilizing building information modeling for better control and management of construction projects. Buildings, 16(7), 1318. https://www.mdpi.com/2075- 5309/16/7/1318

Álvarez-Pozo, A. H., Parma-García, M. I., Ortiz-Marcos, I., Bautista, L. F., & Atanes- Sánchez, E. (2024). Analysis of causes of delays and cost overruns as well as mitigation measures to improve profitability and sustainability in turnkey industrial projects. Sustainability, 16(4), 1449.

Arju, M. A. A. S., & Rahman, T. (2023). A data-driven framework for engineering project risk assessment under schedule and cost uncertainty. International Journal of Scientific Interdisciplinary Research, 4(2), 204–251. https://ijsir.org/index.php/IJSIR/article/download/122/120

Babar, S., Thaheem, M. J., & Ayub, B. (2017). Estimated cost at completion: Integrating risk into earned value management. Journal of Construction Engineering and Management, 143(3), 04016104.

Ekhlasi, T. (2024). The impact of integrated supply chain platforms on project management criteria: A study of time, cost, and risk management in construction projects (Doctoral dissertation, Politecnico di Torino). https://webthesis.biblio.polito.it/30711/

Fawcett, T. (2006). An introduction to ROC analysis. Pattern Recognition Letters, 27(8), 861–874.

Fleming, Q. W., & Koppelman, J. M. (2010). Earned value project management (4th ed.). Project Management Institute.

Haji-Kazemi, S., Andersen, B., & Klakegg, O. J. (2015). Barriers against effective responses to early warning signs in projects. International Journal of Project Management, 33(5), 1068–1083.

Haji-Kazemi, S., Andersen, B., & Krane, H. P. (2013). A review on possible approaches for detecting early warning signs in projects. Project Management Journal, 44(5), 55–69. https://doi.org/10.1002/pmj.21360

Hastie, T., Tibshirani, R., & Friedman, J. (2009). The elements of statistical learning: Data mining, inference, and prediction (2nd ed.). Springer.

Lipke, W. (2003). Schedule is different. The Measurable News, March and Summer issues.

Nardo, M., Saisana, M., Saltelli, A., Tarantola, S., Hoffmann, A., & Giovannini, E. (2008). Handbook on constructing composite indicators: Methodology and user guide. OECD Publishing.

Okoli, C., & Pawlowski, S. D. (2004). The Delphi method as a research tool: An example, design considerations and applications. Information & Management, 42(1), 15–29.

Petraitis, I. (2025). Project management key performance indicators and their determination in organizations (Doctoral dissertation, Vilniaus universitetas).

Sandilya, S. K., & Varghese, K. (2016). A study of delays in procurement of engineered equipment for engineering, procurement and construction (EPC) projects in India: A mixed method research approach. In Y. G. Sandanayake, G. I. Karunasena, & T. Ramachandra (Eds.), Greening environment, eco-innovations & entrepreneurship (pp. 34–43). Ceylon Institute of Builders.

Soliman, E., Alrasheed, K. A., Alghanim, S., & Morsi, E. (2024). Integrating risk management and earned value framework to detect early warning signs—Case study. Journal of Engineering Research. https://www.sciencedirect.com/science/article/pii/S2307187724001421

Vanhoucke, M., & Vandevoorde, S. (2007). A simulation and evaluation of earned value metrics to forecast the project duration. Journal of the Operational Research Society, 58(10), 1361–1374.

Zheng, L., Baron, C., Esteban, P., Xue, R., Zhang, Q., & Yang, S. (2019). Using leading indicators to improve project performance measurement. Journal of Systems Science and Systems Engineering, 28(5), 529–554.